I spoke with Alfonso, the school director, about the items on his wish list and agreed that some of the changes (installing a urinal in the boys bathroom and putting metal doors on the remaining 5 stalls would be too costly at this time. It was suggested that this could be done from a future fundraiser.
The pavers have been installed around the bathrooms and have greatly improved the grounds.
The temporary classroom has not been completed as of this date. Alfonso has applied for government assistance to complete the project and is waiting for a reply.
We would like approval from Amigos de Lo de Marcos for the following work to be preformed at the Primary School.
1. Work to be done on toilets.
2. Work to be done on sinks
3. Bathroom lights
4. Work to be done on water pump (bomba)
5. Work to be done on water tank ( tinaco)
6. Roof Leaks
7. Paint
Costs
Parts 3700.00
Labor 4000.00
Paint 0.00 donated
Painting labor 0.00 donated
------------
TOTAL COSTS 7750.00
Work to be done by William Bravo during summer vacation. (July 3 to August 22)
Painting to be done by volunteers.